Monon Corridor

Monon Corridor
Monon Corridor crossing above Sibley Street, April 2026
Overview
LocaleLake County, Indiana, United States
Termini
Service
TypeCommuter rail
SystemSouth Shore Line
OperatorNICTD
Rolling stockNippon Sharyo NICTD EMUs
History
OpenedMarch 31, 2026 (2026-03-31)
Technical
Line length9 mi (14 km)
Number of tracks1 + passing sidings
Track gauge4 ft 8+12 in (1,435 mm)
ElectrificationOverhead line1,500 V DC
Route map
0
Millennium Station
Metra│NICTD
0.8 mi
1.3 km
Van Buren Street
1.4 mi
2.3 km
Museum Campus/​11th Street
2.2 mi
3.5 km
18th Street
(events only)
2.7 mi
4.3 km
McCormick Place
(events only)
I-55 (End)
7.0 mi
11.3 km
57th Street
14.5 mi
23.3 km
115th Street/​Kensington
(bypassed)
19.0 mi
30.6 km
Hegewisch
Monon Corridor to Chicago
(peak hours)
Lakeshore Corridor
20.7 mi
33.3 km
Hammond Gateway
Maintenance and storage facility
21.9 mi
35.2 km
Downtown Hammond
(planned)
24.1 mi
38.8 km
South Hammond
25.3 mi
40.7 km
Munster Ridge
Amtrak to Chicago
CN South Bend Subdivision
28.1 mi
45.2 km
Munster/Dyer
0.6 miles (1 km) to Dyer
Key
Monon Corridor
Lakeshore Corridor
Metra Electric District
Other lines

The Monon Corridor, also called the West Lake Corridor during project planning and construction, is a commuter rail line in Lake County, Indiana, that is part of the South Shore Line system. The line, which branches south from the main line at Hammond Gateway station along a single-track line, serves the municipalities of Hammond, Munster and Dyer. Trains run directly to Chicago during peak hours, while shuttle trains run between Hammond and Dyer during off-peak hours.

The Northern Indiana Commuter Transportation District (NICTD) began planning an extension of the South Shore Line to Valparaiso in 2006 due to population growth in Northwest Indiana. Plans were canceled in 2008 due to lower-than-expected ridership projections. The Indiana General Assembly approved funding for the branch in 2015, and the Federal Transit Administration awarded a grant to the line in 2019. Work started in October 2020, and the branch had its opening announced in the farewell letter from the retiring NICTD President for March 31, 2026.

History

New Start Studies

In the mid-2000s, the population and commercial growth in Lake and Porter counties in Northwest Indiana was outstripping projections.[1] The Northern Indiana Commuter Transportation District determined that if the growth continued, it would be necessary to add another branch to the South Shore Line commuter rail.[1] In 2006, planning proceeded for an extension to Valparaiso, but the NICTD was unable to confidently attain trackage rights on the Canadian National Railway line to Valparaiso.[2] By 2008 a new study indicated that the Valparaiso to Munster branch would not generate sufficient ridership and was dropped from the plan.[3]

The Indiana General Assembly approved funding in 2015 for the construction of a South Shore Line branch to Dyer.[4][5] The Lake County government and 15 of the county's towns agreed to provide funding for the branch.[5] In 2017, the NICTD began demolition of houses between Hanover and Brunswick streets to begin building the new Hammond Gateway station, where trains would interchange with the main line.[6] The same year, the NICTD modified its plans for the West Lake Corridor, adding a maintenance barn to the proposed Hammond Gateway station and relocating the proposed Munster Ridge station.[7]

Capital Investment Grant Program

In March 2019, the Federal Transit Administration (FTA) gave the project a favorable rating meaning the project could qualify for funding from the Capital Investment Grant Program. NICTD anticipated to be awarded funding the following spring with construction beginning later in the year.[8] That October, the FTA approved the project moving it into its engineering phase.[9] The project was to cost $945 million, including $335 million from local sources, $255 million in state funds, and $355 million in federal funds.[10][11]

Construction

A groundbreaking ceremony was held on October 28, 2020, which included the signing of a full funding grant between the FTA and NICTD.[12][13] By July 2023, thirty-five percent of the project was finished;[14] By November 2024, ninety percent of the work had been finished.[15]

Although the project was called the West Lake Corridor, as far back as 2023, NICTD planned to adopt the Monon Corridor name to refer to the new branch.[16][17]

In July 2023, NICTD's president Mike Noland said the West Lake Corridor could open as early as May 2025, as long as an underpass near the Dyer station was completed on schedule.[14] The underpass's construction had been delayed due to the lack of approval from CSX Transportation, which owned the right-of-way of the rail line being crossed. Consequently, the underpass was not planned to be completed until September 2025.[18][19] By June 2025, the line was expected to open before the end of the year.[20] Later that September, transformers on the line were found to be damaged following a storm, although NICTD determined that the damages were not caused by the storm. As a result of the damages, the project was delayed to early 2026.[21][22] Test trains were being operated by late 2025 and early 2026.[23][24] On March 13, 2026, the branch's opening was set to March 31 in a farewell letter from the retiring NICTD's president Mike Noland.[25][26] The line began operation on March 31, 2026, as scheduled.[27][28][29]

Alignment

Traveling southbound, the new branch leaves the existing main line immediately before Hammond Gateway station.[30] From Hammond south, the line follows the route of Monon Trail until it reaches Maynard Junction. The Monon Trail was retained, but follows a new alignment.[30] At Maynard Junction, the Corridor has a flyover over the EJ&E/CSX tracks, and then follows new tracks built immediately west of the CSX right-of-way.

The Monon Corridor is single-tracked with a passing loop between Hammond and Munster.

The line, extending to the town of Dyer, runs for about 8 miles (13 km).[31] Due to financial constraints, the initial segment did not extend to St. John or Lowell, but provisions have been made for future extension.[32] NICTD has also proposed extending the line further south to serve Lowell, St. John, and Cedar Lake, but as of 2024 there are no specific plans to carry out this extension.[31]

The line contains four stations in addition to a maintenance facility in Hammond.[10] NICTD did not construct a station serving Hammond's downtown area. However, as part of a plan to revitalize its downtown, the city of Hammond plans to construct a downtown station itself at Russell Street along a section of elevated track. This station was initially proposed to be located south of the federal courthouse, but the site was later moved two blocks north to facilitate better pedestrian access to the downtown core.[33] Because the West Lake Corridor project had already received environmental approval, Downtown Hammond will be an infill station built after the initial opening of the line, though preparatory work (including provisions for a pedestrian access tunnel) was completed along with the rest of the initial West Lake Corridor project.[34][35] In the summer of 2024, the City of Hammond selected an architect to design the downtown infill station. A groundbreaking ceremony was held on April 16, 2026.[36]

Station listing

Fare
zone
Location Station Connections and notes
4 Hammond Hammond Gateway
Downtown Hammond Future infill station
South Hammond
5 Munster Munster Ridge
Munster/Dyer

Service patterns

Most Monon Corridor trains operate as semi-hourly shuttle trains between the terminus at Munster/Dyer station and Hammond Gateway station, where passengers can transfer to Lakeshore Corridor trains with a wait of 10–15 minutes. During peak times, five trains run directly between Munster/Dyer and Millennium Station in downtown Chicago, in the direction of rush hour travel. Additionally, one reverse peak train runs during both the morning and evening rush hours. These through trains skip Hammond Gateway Station, but make all other regular South Shore Line stops between Millennium Station and Munster/Dyer Station.[37]

See also

References

  1. ^ a b Benman, Keith (June 23, 2006). "Study: South Shore extension would add jobs, income". nwi.com. Retrieved July 16, 2017.
  2. ^ "Archived copy". WJOB (Calumet)/AP. Archived from the original on July 26, 2012. Retrieved September 11, 2006.{{cite web}}: CS1 maint: archived copy as title (link)
  3. ^ Benman, Keith (December 17, 2008). "Study: Valpo-to-Munster SS line would add few riders". nwi.com. Retrieved July 16, 2017.
  4. ^ "State spurns extra South Shore funding". Salina Journal. December 15, 2015. Retrieved January 29, 2025.
  5. ^ a b Arvia, Katie (April 11, 2022). "West Lake Corridor Project to give Lansing and Munster easier train access to Chicago". The Lansing Journal. Retrieved January 29, 2025.
  6. ^ Gonzalez, Michael. "Train plans unsettle Hammond neighborhood". Chicago Tribune. Retrieved July 18, 2020.
  7. ^ "South Shore Line Announces Updated Station Plans for West Lake Corridor Project". Portage.Life. May 15, 2017. Retrieved January 30, 2025.
  8. ^ "FTA gives favorable rating to proposed NICTD commuter-rail extension". Progressive Railroading. March 26, 2019. Retrieved March 26, 2019.
  9. ^ Keiper, Jennifer (October 8, 2019). "FTA Gives South Shore Line Expansion A Thumbs Up". WBBM-AM. Retrieved October 15, 2019.
  10. ^ a b Dmitrovich, Nick (April 23, 2021). "West Lake Corridor Construction is Rolling". Building Indiana Business. Retrieved January 29, 2025.
  11. ^ Mills, Wes (June 6, 2022). "Decades in the Making, West Lake Rail Project is Underway". Inside INdiana Business. Retrieved January 29, 2025.
  12. ^ Brown, Alex (October 28, 2020). "Work to Begin on West Lake Corridor Project". Inside INdiana Business With Gerry Dick. Retrieved November 1, 2020.
  13. ^ Steele, Andrew (October 28, 2020). "WATCH NOW: 8-mile rail line from Hammond to Dyer is on way". nwitimes.com. The Times of Northwest Indiana. Retrieved November 12, 2020.
  14. ^ a b Mills, Wes (July 7, 2023). "Progress continues on Double Track, West Lake Corridor". Lakeshore Public Media. Lakeshore Public Media. Retrieved August 27, 2023.
  15. ^ Ross, Doug (November 26, 2024). "West Lake Corridor work 90% complete; commuter train service to start by fall 2025". Chicago Tribune. Retrieved January 29, 2025.
  16. ^ Gallenberger, Michael (October 2, 2023). "First section of South Shore Line's Double Track to open in coming weeks". Lakeshore Public Media. Retrieved June 15, 2024. Noland says the railroad plans to use the 'South Shore Line' to refer to its entire system, with the existing service being called the 'Lakeshore Corridor' and the West Lake branch being the 'Monon Corridor.'
  17. ^ "NICTD: Regular train service set to resume between Dune Park and MC in two weeks, shortening bus rides". Chicago Tribune. October 2, 2023. Retrieved June 15, 2024.
  18. ^ "Underpass work will determine opening date for South Shore's West Lake branch". Trains. November 27, 2024. Retrieved January 29, 2025.
  19. ^ Gallenberger, Michael; Media, Lakeshore Public (November 26, 2024). "South Shore president not ruling out May opening of West Lake Corridor". Inside INdiana Business. Retrieved January 29, 2025.
  20. ^ "Launch of South Shore's West Lake service may not come this year". Trains. June 9, 2025. Retrieved June 12, 2025.
  21. ^ Ross, Doug (September 29, 2025). "Transformers temporarily derail West Lake Corridor service". Chicago Tribune. Retrieved March 31, 2026.
  22. ^ Ross, Doug (October 1, 2025). "South Shore Line's transformers trouble not tied to storm". Chicago Tribune. Retrieved March 31, 2026.
  23. ^ "South Shore Line Electric Train Testing on Monon Corridor". Indiana 105. December 18, 2025. Retrieved January 14, 2026.
  24. ^ "South Shore stages dynamic tests on new Monon Corridor". Trains. January 3, 2026. Retrieved January 14, 2026.
  25. ^ Pfundstein, Heather (March 14, 2026). "Noland's last words: Monon opens March 31". Northwest Indiana Business Magazine. Retrieved March 31, 2026.
  26. ^ Gallenberger, Michael (March 15, 2026). "Retiring NICTD president announces opening date of Monon Corridor". WVPE. WVPE. Retrieved March 20, 2026.
  27. ^ "South Shore Line to Munster and Dyer starts March 31". Chicago Crusader. March 30, 2026. Retrieved March 31, 2026.
  28. ^ "South Shore Line to Begin Service on New Monon Corridor". Indiana 105. March 30, 2026. Retrieved March 31, 2026.
  29. ^ Ross, Doug (March 31, 2026). "Trains now running along Monon Corridor; South Shore Line dedicates route between severe storms". Chicago Tribune. Tribune Publishing. Retrieved April 2, 2026.
  30. ^ a b "Frequently Asked Questions". West Lake Corridor. 2017. Retrieved July 16, 2017.
  31. ^ a b Brown, Alex (May 14, 2024). "What's next for the South Shore Line?". Inside INdiana Business. Retrieved January 29, 2025.
  32. ^ Simón, Marisol R.; Noland, Michael; Federal Transit Administration; USDoT; US Army Corps of Engineers (December 2, 2016). West Lake Corridor Draft Environmental Impact Statement (Chapter 2: Alternatives Considered) (PDF) (Report). NICTD. p. 5. Retrieved July 16, 2017. The alignments by alternative were evaluated from cost, feasibility, and freight railroad acceptability perspectives. The analysis concluded that the alignment between Dyer and St. John should be dropped from further consideration primarily because the estimated capital cost would have exceeded the funding that has been identified for the project. It was understood that an extension to St. John or Lowell could be considered in the future.
  33. ^ "Hammond Downtown Master Plan". CNU. July 19, 2023. Retrieved March 11, 2026.
  34. ^ Steele, Andrew (March 13, 2022). "Decades of hopes and plans culminate with start of South Shore projects". nwitimes.com. The Times (Munster, Indiana). Retrieved May 25, 2022.
  35. ^ Zorn, Tom (March 25, 2022). "Municipalities get on board plans to grow housing, commercial developments as South Shore projects start". Chicago Tribune. Retrieved May 25, 2022.
  36. ^ "Downtown Station Groundbreaking".
  37. ^ "NICTD South Shore Line Schedule". April 1, 2026.