Yamanashi Prefecture Station

Yamanashi Prefecture Station

山梨県駅
General information
Operated by JR Central
LineChūō Shinkansen
Platforms2 Island platforms
Tracks4
Key dates
Construction start date11 March 2026[1]
Projected completion date10 December 2031
Location

The Yamanashi Prefecture Station (Japanese: 山梨県駅, Hepburn: Yamanashi-ken-eki) is the tentative name for a planned station on the Chūō Shinkansen, which will be operated by JR Central.[1] The station will be located in Kōfu, Yamanashi Prefecture.

The station is projected to be completed by 10 December 2031.

History

The planned station's location in Ōtsu-machi, Kōfu was decided in 2011 as requested by Yamanashi Prefecture following consultations with local business organizations.[2] JR Central signed contracts with Meiko Construction, Tekken, and Hayano to construct the station, and the surrounding viaducts on 17 September 2025. The construction is expected to start by the end of 2025, and is planned to be completed by 10 December 2031.[3] Due to construction delays in Shizuoka Prefecture, the station will not be able to officially open for around four years until the entire line opens in 2035.[4]

In February 2026, NHK reported that a ceremony to mark the start of station construction would be held the following month, with Yamanashi Prefecture Governor Kotaro Nagasaki in attendance.[1]

Details

The planned station will be elevated, with four tracks and two island platforms.[5] The station will only be served by the Chūō Shinkansen, located about 3 kilometres (1.9 miles) away from the nearby Koikawa Station on the Minobu Line. There is a plan to connect the station to the Chūō Expressway by an interchange, and shuttle buses will connect the station to Koikawa Station and Kōfu Station.[6]

References

  1. ^ a b c "JR Central to begin construction of final maglev station in Yamanashi next month". NHK. 9 February 2026. Archived from the original on 9 February 2026. Retrieved 10 February 2026.
  2. ^ "リニア山梨駅、甲府に決定 再検証1年「元のサヤ」に". 日本経済新聞 (in Japanese). The Nikkei. 2020-01-19. Retrieved 2025-09-20.
  3. ^ "JR東海、リニア山梨県駅の工事契約締結 名工建設などのJVと". 日本経済新聞 (in Japanese). The Nikkei. 2025-09-17. Retrieved 2025-09-20.
  4. ^ 孝, 平尾 (2025-09-17). "リニア山梨県駅、完成時期明確化で部分開通待望論が強まる 実験線駅としての活用案など". 産経新聞:産経ニュース (in Japanese). Retrieved 2025-09-20.
  5. ^ "中央新幹線品川・名古屋間事業説明会" (PDF) (in Japanese). Retrieved 20 September 2025.
  6. ^ "「非常に珍しい新幹線駅」いよいよ工事着手へ 高速道路の「スマートIC」が駅直結! 完成はいつ?". 乗りものニュース (in Japanese). 2025-09-18. Retrieved 2025-09-20.