Mass Central Rail Trail—Wayside
| Mass Central Rail Trail—Wayside | |
|---|---|
Mass Central Rail Trail—Wayside at former East Sudbury station site, a portion of the 7.6 mile Sudbury to Hudson build. May 2025 | |
| Length | 16 miles (26 km) open, 23 miles (37 km) when complete |
| Location | Waltham, Massachusetts to Berlin, Massachusetts |
| Established | 2010 DCR lease for construction signed, 2014 first MCRT—Wayside section built |
| Use | Hiking, bicycling, inline skating, wheelchairs, strollers, cross-country skiing, horseback riding |
| Difficulty | Easy |
| Season | Year-round |
| Surface | Paved, stone dust (to be paved), unimproved |
| Right of way | MBTA owned, former Massachusetts Central Railroad and later Central Mass Branch |
| Maintained by | Department of Conservation and Recreation |
| Website | mass masscentralrailtrail |
| Trail map | |
DCR's Mass Central Rail Trail—Wayside in progress Purple: In Design Green: Complete | |
The Mass Central Rail Trail—Wayside (MCRT—Wayside) is a partially completed, 23-mile (37 km) rail trail in Waltham, Weston, Wayland, Sudbury, Marlborough, Hudson, Stow, Bolton, and Berlin, Massachusetts. The trail is a Department of Conservation and Recreation (DCR) state park along the right-of-way (ROW) of the former Massachusetts Central Railroad and later, former MBTA Central Mass Branch.[1] The MCRT—Wayside currently has 16 miles (26 km) open, and the remaining miles are in design. The MCRT—Wayside is part of the 104-mile (167 km) Mass Central Rail Trail between Boston and Northampton.
Trail overview
All 23 miles (37 km) of the MCRT—Wayside, once built, form a state park owned by the MBTA and maintained by the DCR, except for a 0.75-mile (1.21 km) section owned and maintained by the Town of Hudson, as it is shared with the Assabet River Rail Trail.[1][2]: 10–11 As of 2026, the MCRT—Wayside has 16 miles (26 km) open—representing 71% of the total route—while the remaining 29% is currently in design. All completed sections of the MCRT—Wayside are paved, and DCR plans to pave both all sections under construction and the only section that is currently stone dust in Wayland.[3][4]: 45 While the MBTA ROW is 50 to 100 feet (15 to 30 m) wide, DCR leased trail sections are 19 feet (5.8 m) wide, known as the "Path Development Corridor", consisting of a paved path, typically 10 or 12 feet (3.0 or 3.7 m) wide, with grass shoulders, grading, and additional side clearance.[5]: 8 [6]: 5 [7]: 11–7, 11–8
Trail details
Mass Central Rail Trail—Wayside | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Segment endpoints | Municipality | Length | Surface | Status | Year opened |
|---|---|---|---|---|---|
| Beaver Street to Border Road (Except Linden Street Bridge) |
Waltham | 2.75 miles (4.4 km) |
Paved | Complete | 2023 |
| ↳ Linden Street Bridge | Waltham | 0.02 miles (0.04 km) |
Paved | Complete | 2025 |
| Border Road to Hillside Road | Waltham | 0.3 miles (0.48 km) |
Paved | Complete | 2014 |
| Hillside Road to Jones Road | Waltham | 0.5 miles (0.80 km) |
Unimproved | In Design | |
| Jones Road to Stony Brook Bridge | Waltham, Weston | 0.3 miles (0.48 km) |
Paved | Complete | 2025 |
| Stony Brook Bridge to Cochituate Road | Weston, Wayland | 4.4 miles (7.1 km) |
Paved | Complete | 2019 |
| Cochituate Road to Route 20 | Wayland | 0.5 miles (0.80 km) |
Stone dust | Complete | 2017 |
| Route 20 to Sudbury substation | Wayland, Sudbury | 1.4 miles (2.3 km) |
Unimproved | In Design | |
| Sudbury substation to Wilkins Street | Sudbury, Marlborough, Stow, Hudson | 7.6 miles (12.2 km) |
Paved | Complete | 2025 |
| Wilkins Street to Priest Street (Shared with Assabet River Rail Trail) |
Hudson | 0.75 miles (1.2 km) |
Paved | Complete | 2005 |
| Priest Street to Felton Street | Hudson | 1.0 mile (1.6 km) |
Unimproved | In Design | |
| Felton Street to Hudson/Bolton Line | Hudson | 1.6 miles (2.6 km) |
Unimproved | In Design | |
| Hudson/Bolton line to Coburn Road | Bolton, Berlin | 2.3 miles (3.7 km) |
Unimproved | In Design |
Waltham
Beaver Street to Border Road
Status: Complete | Length: 2.75 miles (4.43 km) | Surface: Paved
In Waltham, the MCRT—Wayside begins at Beaver Street, at the location of the former Clemantis Brook Station, and this section is complete.[8]: 3 Waltham funded the approximately $9 million cost of construction of its section from City revenues.[9][10] Construction began in 2022 and was substantially complete by September 2023.[11][12] The timber trestle bridge over Clemantis Brook was rehabilitated with new decking and timber bridge railings, stone abutments, and concrete piles. This section passes by Waltham Highlands station. From Beaver Street to the Linden Street bridge, it is an example of rails with trails with the MBTA Fitchburg Line.
Linden Street Bridge
Status: Complete | Length: 120 feet (37 m) | Surface: Paved
The Linden Street Bridge rehabilitation, in-between the Waltham section above, is complete.[13] Waltham received matching MassTrails grants in 2022 and 2023 to fund construction, however DCR eventually funded reconstruction of the bridge.[14]: 9 [15]: 11 [1] The bridge was built in 1894 and is a lattice truss bridge on granite abutments.[16]: 3–5 In 2002, the Wayside Rail Trail Committee held the Golden Spike 2002 event adjacent to the bridge, where statewide advocates unified on the Mass Central Rail Trail name for the greater project between Boston and Northampton.[17] Construction began in December 2024 and completed in December 2025.[18][19][20]
Border Road to Hillside Road
Status: Complete | Length: 0.3 miles (0.48 km) | Surface: Paved
This Waltham section from slightly east of Border Road to Hillside Road was the first completed section of the MCRT—Wayside. It was built in 2014 in partnership with the 1265 Main Street Phase 1 development.[21]
Hillside Road to Jones Road
Status: In Design | Length: 0.5 miles (0.80 km) | Surface: Unimproved
This Waltham section is unimproved. This section will rehabilitate the existing bridge over Rt. 128. The bridge was built in 1960 and is a two-span plate girder bridge on concrete abutments and pier.[16]: 6–7 This section is at 25% design.[22] It is being designed in coordination with the 1265 Main Street Phase 2 mixed use development and roadway improvements project. The roadway improvement portion of the 1265 Main Phase 2 project will occur before the MCRT—Wayside project, and the timeline of both projects remains undetermined as of March 2026.[1] The 1265 Main Phase 2 project will create a new shared use path on Route 117 and Green Street, prior to the more direct MCRT—Wayside over the Rt. 128 bridge rehabilitation.[22][23] The 1265 Main Phase 2 project also considers relocating the Kendal Green MBTA commuter rail station to Jones Road to create a multi-modal center integrated with the trail.[24]: 9, 17
Waltham, Weston, Wayland, Sudbury
Jones Road to Stony Brook Bridge
Status: Complete | Length: 0.3 miles (0.48 km) | Surface: Paved
The section from Jones Road, Waltham to slightly west of the Stony Brook Bridge over the MBTA Fitchburg Line in Weston, is complete.[22] This section rehabilitated the existing Stony Brook bridge over the MBTA Fitchburg Line.[25] The Stony Brook bridge was built in 1896 and is a riveted lattice truss bridge on stone abutments.[16]: 8–9 The design of the bridge was based on the Norwottuck Rail Trail Bridge along with the Linden Street Bridge, and the three are the only remaining examples of riveted lattice truss bridges in Massachusetts.[26][27] In December 2023, Governor Maura Healy announced leftover American Rescue Plan Act funding would be used for construction, and DCR issued a notice to proceed in 2024.[28][29] Construction completed in August 2025.[30][1]
Stony Brook Bridge to Cochituate Road
Status: Complete | Length: 4.4 miles (7.1 km) | Surface: Paved
The section from slightly west of the Stony Brook Bridge in Weston to Cochituate Road, Wayland is complete. DCR paved the access road and installed safe road crossings in 2019, in partnership with Eversource and Weston.[31]: 28 [32][33] This section passes by the historic Wayland Freight House and Weston Depot.[34]
Cochituate Road to Route 20
Status: Complete | Length: 0.5 miles (0.80 km) | Surface: Stone dust
This Wayland section is complete with a stone dust surface. It was installed as a stone dust trail by the Town of Wayland in 2017, and includes a historic railway turntable to be preserved.[31]: 56 [3]: 26 The surface is planned to be paved during the Wayland to Sudbury project, which is scheduled to begin construction in Winter 2027. This section passes by Wayland station.
Route 20 to Sudbury substation
Status: In Design | Length: 1.4 miles (2.3 km) | Surface: Unimproved
The section from Route 20 in Wayland to the Eversource Sudbury substation to is unimproved. This section received State funding for construction in 2021, and as of 2023 is at 25% design to construct a paved trail.[35][3]: 15 The ETA for the start of construction is Winter 2027.[3]: 36 [36] DCR once hoped to move the date forward to better align with the Sudbury-Hudson section's construction and completion.[37] There is a timber trestle bridge over the Sudbury River.[16]: 22–24 The trail will offer scenic views of the Great Meadows National Wildlife Refuge including a planned timber lookout, but the Great Meadows hiking trails will not directly connect to the MCRT.[3]: 23
Sudbury, Marlborough, Stow, Hudson
Sudbury substation to Wilkins Street
Status: Complete | Length: 7.6 miles (12.2 km) | Surface: Paved
The section from the Eversource Sudbury substation to Wilkins Street in Hudson was completed in 2025, passing through Sudbury-Marlborough-Hudson-Stow-Hudson in east to west order.[1] Eversource's buried power line construction, which included the pedestrian bridges and a gravel access road, was completed in November 2024. Bridge 127 in Sudbury was a riveted plate deck girder bridge, built in 1881. Over time, it had submerged into Hop Brook, damaging the piers and steel, and making it unsafe for the MCRT. Bridge 130 over Fort Meadow Brook in Hudson was a timber trestle bridge, destroyed by fire in 2019.[38]: 4 Both bridges were replaced by prefabricated structural steel truss bridges in 2024. Bridge 128, also over Hop Brook in Sudbury, was built in 1881. It is a riveted plate deck girder bridge with granite abutments and timber piers.[16]: 10–14, 25–27 It received a new timber deck and railing, preserving the girders, piers, cross frames, and the majority of the abutments.[38]: 4–5 A new precast arch pedestrian tunnel was installed under Chestnut Street in Hudson.[39] This section passes by South Sudbury station adjacent to the former railroad crossing, with tracks forming a diamond that was preserved inside a new trail roundabout, and the historic Sudbury Section Tool House.[40][41] The Stow section is 327 feet (100 m) between Wilkins Street, Hudson and Chestnut Street, Hudson.[8]: 2 The Marlborough section is several feet to the center of the trail, forming a tripoint with the Hudson and Sudbury borders. It is accessible from Marlborough by the Old Concord Road hiking path.[42] The Wayside Inn Railroad Waiting Room was a B&M station at the Dutton Road crossing for which the MCRT—Wayside is named.[43] DCR acquired American Rescue Plan Act funding for construction which began in February 2025 and paved the trail.[44] While completed in 2025,[1] additional roadway crossing improvements are estimated to be added in Spring 2026.[45]
Hudson
Wilkins Street to Priest Street
Status: Complete | Length: 0.75 miles (1.21 km) | Surface: Paved
This Hudson section was completed as part of the Assabet River Rail Trail (ARRT) built by 2005, except for the MA-62 bridge over the Assabet River which was rebuilt in 2010.[46] Hudson designated this ARRT section to be shared with the MCRT—Wayside by 2023. This arrangement is a cost saving measure, including eliminating the cost of rehabilitating a timber trestle bridge over the Assabet River to the northwest of the section.[2]: 10–11 [16]: 19–21 The unimproved ROW, intersecting the completed trail at the former Gleason Junction, runs northwest and southeast.
Priest Street to Felton Street
Status: In Design | Length: 1 mile (1.6 km) | Surface: Unimproved
The downtown Hudson section is unimproved.[2]: 10 This section includes a timber trestle bridge over Bruce's Pond used by pedestrians, despite the unimproved state.[16]: 17–18 In 2023 and 2025, MassTrails grants were awarded for design of this section and the west Hudson section.[15]: 6 [47][48] In June 2025, Hudson announced full funding for 100% design of this section.[49]
Felton Street to Hudson/Bolton Line
Status: In Design | Length: 1.6 miles (2.6 km) | Surface: Unimproved
The west Hudson section is unimproved.[2]: 10 In 2023 and 2025, MassTrails grants were awarded for design of this section and the downtown Hudson section.[15]: 6 [47][48] Design work for this section will proceed following design for the downtown Hudson section.[49]
Bolton, Berlin
Hudson/Bolton line to Coburn Road
Status: In Design | Length: 2.3 miles (3.7 km) | Surface: Unimproved
This section from the Hudson/Bolton line to Coburn Road in Berlin is unimproved, overgrown, and is missing some original bridges. The brief Bolton section is just 100 feet (30 m).[8]: 2 In 2024, a MassTrails grant for preliminary design of this MCRT—Wayside section was awarded, as well as a feasibility study for all of the MCRT in Berlin to the Clinton border.[50]: 2 There is no known ETA for construction. An advocacy group, Berlin Trail Trust, is promoting the construction of the Mass Central Rail Trail in Berlin.[51]
Connecting trails
MCRT connections
As a part of the Mass Central Rail Trail (MCRT) from Boston to Northampton, in design segments of the MCRT will connect to the MCRT—Wayside in both directions. Heading east, after a short unimproved section from Beaver Street to the Belmont border, the Belmont Community Path (BCP) is in design.[52] After the BCP, the MCRT is complete to Boston through many paths and parks, including the Fitchburg Cutoff Path, the Cambridge Linear Park, and the Somerville Community Path. Heading west, the Berlin Rail Trail is in design,[53] as is the MCRT in Clinton,[54] before reaching completed MCRT sections starting with the Wachusett Dam Hike and the MCRT sections built by Wachusett Greenways.
Additional trail connections
In Hudson, the MCRT—Wayside connects with the Assabet River Rail Trail and the Marlborough-Sudbury State Forest/Goodale Lot hiking trails.[55] In Sudbury, it connects with the Bruce Freeman Rail Trail Phase 2D, at the site of the Sudbury diamond. There are also many connections to hiking trails including the Assabet River National Wildlife Refuge, the City of Marlborough Desert Natural Area, the Town of Sudbury Hop Brook Marsh Conservation Land, and Sudbury Valley Trustees Memorial Forest.[56] In Wayland, a portion of the trail is shared with the Bay Circuit Trail and the East Coast Greenway. In Weston, there are many connections to hiking trails including Jericho Town Forest and Sears Conservation Land.[57] In Waltham, there is a connection to the hiking trails in Prospect Hill Park. The Western Greenway to MCRT connection received a 2023 MassTrails grant for design and permitting.[15]: 11 [58]
History
By 1971, passenger service on the Central Mass Branch west of Waltham, subsidized by the Massachusetts Bay Transportation Authority (MBTA) since 1964, had ended due to low ridership.[59]: 369–370, 373 In 1972, Governor Francis Sargent initiated a Commuter Rail Improvement Program which concluded that, while too early to restore service on the Central Mass Branch, acquisition from the Boston and Maine Railroad (B&M) to preserve the Central Mass Branch ROW and other ROWs would be prudent.[60]: 143 In December 1976, the MBTA purchased from B&M 270 miles (430 km) of ROW across Massachusetts for $39.5 million, although 130 miles (210 km), including the Central Mass Branch, were not in commuter rail service.[61] B&M retained various freight rail service obligations over the ROWs for several more years.[62] By 1977, the MBTA had acquired title ownership of all of these ROWs in fee simple, a portion from the 1976 purchase and a portion by order of taking.[63][64][65] By 1980, a permanent discontinuance of the B&M's freight obligations for the Central Mass Branch west of Waltham was approved. The final train on the Central Mass Branch ROW, freight in Waltham between Bacon Street and Clematis Brook, ran in 1994.[60]: 137–138 In 1996, the MBTA produced the "Central Mass. Commuter Rail Feasibility Study", which advised reactivation of the Central Mass Branch between Berlin and Waltham would not be cost effective.[66]: 51 In 1997, a "Central Massachusetts Rail Trail Feasibility Study" was commissioned for $30k by the Massachusetts Turnpike Authority, which found construction of a 25-mile (40 km) trail to be feasible.[67][68]: vii-viii The proposed trail was quickly renamed the Wayside Rail Trail by the Wayside Rail Trail Committee, a 501(c)(3) nonprofit, as the Wayside Inn / Wayside Inn Railroad Waiting Room was a B&M station at the crossing with Dutton Road.[43][69] All seven municipalities from Berlin to Belmont (excepting Bolton, Stow, and Marlborough, as their shortest sections were expected to be bundled with their surrounding sections) initially approved the trail by large margins. However, a follow up Weston Special Town meeting voted 698 against and 410 in favor, which derailed progress on the Wayside Rail Trail for at least two decades.[31]: 23–24, 26 [70][71][72] In 2006, theft of a section of rail was discovered in Berlin, which encouraged the MBTA to take a more active role maintaining the property.[73] By 2010, the DCR executed a 99-year lease with the MBTA to build what was finally renamed the Mass Central Rail Trail—Wayside, combining the Wayside name with the future vision of the Mass Central Rail Trail from Boston to Northampton. The MCRT—Wayside lease is 23 miles (37 km) from Berlin to Waltham.[31]: 6 Under the terms of the lease, the MBTA retains the right to reactivate commuter rail.[74]: 4 This arrangement is not the Federal law known as railbanking because the MBTA neither began the required precondition of abandonment, nor consented to railbanking, which is optional.[75]: 6 In 2014, the Massachusetts Executive Office of Energy and Environmental Affairs (EOEEA) determined the trail did not require further Massachusetts Environmental Policy Act review, simplifying permitting.[31]: 6 [8]
History in Weston and Wayland
In 1951, the Boston Edison Company (BECo) acquired an easement along this section of the B&M's ROW and built overhead power lines.[31]: 57 In 2016, BECo's successor, Eversource, filed permits to build a gravel access road for the power lines over what had become the MBTA's ROW. This included a trail section running from Cochituate Road in Wayland to slightly west of the Stony Brook Bridge over the MBTA Fitchburg Line in Weston.[31]: 27–28 [25] This reduced construction costs of the trail by about $2 million, and in partnership, the DCR made the decision in January 2017 to build the trail by paving the access road and installing safe road crossings, which completed in 2019.[31]: 28 [76][77] Eversource approached Weston for cooperation, sparking Weston's decision to participate, reversing the negative 1997 Town vote. Weston assisted construction by forming a Rail Trail Committee and providing recommendations, officially thanked DCR and Eversource for their contributions to the trail, and now supports the completion of the entire MCRT.[4]: 44–45 [78][79] At Conant Road, the former wooden bridge built in 1937 was demolished and filled with dirt in 1988.[31]: 43–44 With public concern the original design lacked funding for a safe passing of Conant Road,[31]: 44 Weston performed a feasibility study for the underpass in 2017, which was completed in partnership with DCR in 2019.[33]
History in Sudbury, Hudson, and Stow
Based on a 2013 forecast, in 2015 ISO New England issued a Greater Boston area needs assessment, directing utility companies to investigate a series of transmission projects to improve electrical grid reliability, including a connection of the Eversource substation in Sudbury to Hudson Light & Power.[80]: 16–17 Beginning in January 2014, Eversource conducted meetings with federal, state, and municipal officials regarding routing the potential Sudbury to Hudson Transmission Reliability Project.[80]: 70 In September 2014, Sudbury Town Meeting voted in strong support of advancing the MCRT, and in December 2014 voted in overwhelming support to make all reasonable efforts to secure funding for a paved surface MCRT.[80]: 160–161 [81]: 113–115 In January 2015, Sudbury officials noted a Eversource route along the MBTA ROW, either overhead or underground, was an opportunity for construction of the MCRT—Wayside at no cost to the town.[82][83] With the news of a possibility to build the trail without local funding, Sudbury officials and a May 2015 Town vote decided against local funding efforts to accelerate a proposed trail build with a crushed stone surface first.[82][84]: 85 [80]: 161 By November 2015, Sudbury and Hudson officials had formally requested Eversource evaluate an underground design for the transmission lines along the MBTA ROW, which Eversource did by February 2016.[85][86]: 4, 6 By January 2017, the MBTA required this underground route as part of an option agreement with Eversource, at the cost of forgoing approximately $2 million compared to an overhead option. The MBTA also required Eversource to work with DCR to create a trail.[87] In turn, in April 2017, when Eversource sought project approval from the Massachusetts Energy Facilities Siting Board (EFSB), Eversource preferred such an underground MBTA ROW route, though as part of the approval process, Eversource was required to evaluate alternative options. Only the preferred, underground MBTA ROW route was endorsed by the DCR.[88] The underground transmission project benefited DCR by reducing trail construction costs in the range of $6 to $10 million, and required Eversource to make several bridge improvements the trail required.[80]: 160 [88] The Town of Stow Conservation Commission unanimously endorsed the buried transmission project in 2017, in part because it would help build the MCRT.[89][80]: 162 The preferred underground MBTA ROW route was approved by the EFSB in 2019. The EFSB decision noted the associated benefits of the trail, but stated the EFSB's approval of the transmission project was independent of the trail benefits.[80]: 163–164 Designed and permitted in partnership with the DCR, the Eversource project built a gravel sub-base for the trail and grass shoulders, restored or rebuilt three trail bridges, and built a trail tunnel under Chestnut Street in Hudson. Restorative work included mechanical removal of 3.5 acres of invasive plants, the installation of over 2000 native woody plants, and existing vernal pool enhancements.[90] Eversource originally expected to complete the buried power project in December 2019, however the start of construction was pushed to October 2022 and completed in November 2024, due to an unexpectedly lengthy permitting process.[91][92] DCR acquired American Rescue Plan Act funding for construction, which began in February 2025 and paved the trail surface.[44] DCR completed the trail segment in 2025, which included the restoration of selected historical railroad features.[1][93][94]
Litigation
From 2017 to 2022, many lawsuits and petitions were filed by the Town of Sudbury and various abutters alleging the overlapping and jointly permitted construction suffered from varied legal defects, including allegations that the MBTA-DCR trail easement was unlawful and void.[91][75]: 1 [95]: 4, 6 However, in every ruling, all judges determined all plaintiffs could not succeed with any claim.[96][91][97][98][65][99][100][75][95] In 2022 and 2023, abutters sued the MBTA in Massachusetts Land Court twice alleging property rights over the MBTA's Central Mass Branch property in furtherance of such allegations, but withdrew both cases before a judicial ruling.[101][102][95]: 6 In 2024, Hudson Town meeting voters rejected four citizen petitions to sell or lease the MBTA's Central Mass Branch property. The Hudson Finance Committee stated this was an attempt to bring the town into "unnecessary and costly" conflict with the MBTA regarding the ownership of the parcel.[103][104]: 3, 27–28 [105]: 3 While the Towns of Sudbury and Hudson initially opposed construction of the trail at least as jointly permitted with the power reliability project, by 2025 both Town governments had officially endorsed the Sudbury-Hudson trail, and lobbied for the completion of the entire 104-mile (167 km) MCRT.[106][107]
History of Assabet River Rail Trail sharing
In Hudson, a 0.75-mile (1.21 km) section of the MCRT—Wayside is shared with the Assabet River Rail Trail along the former Marlborough Branch of the Fitchburg Railroad.[108][2]: 10–11 Like this trail section, the predecessor railroads also shared this ROW, as some B&M Central Mass passenger trains were run via the Marlborough Branch starting in 1902. This was reduced to Hudson station in 1958, and while subsidized by the MBTA starting in 1964, the final passenger train on the Marlborough Branch ran in 1965.[59]: 369–370 [60]: 161 The MBTA's 1976/1977 purchase/acquisition of various ROWs included the Marlborough Branch along with the Central Mass Branch.[59]: 375–376 [65] B&M ran the final freight train to Hudson on the Marlborough Branch in 1980.[60]: 137
References
- ^ a b c d e f g h Autler, Gerald. "Mass Central Rail Trail—Wayside". Department of Conservation and Recreation. Retrieved 2026-02-25.
- ^ a b c d e "Final Report of the Ad-hoc Bicycle and Pedestrian Committee". Hudson, Massachusetts. 2023-01-23. Retrieved 2024-10-05.
- ^ a b c d e Lavallee, Carrie (2023-03-02). "Mass Central Rail Trail (MCRT) – Wayland to Sudbury, Shared Use Path Virtual Design Public Hearing". State of Massachusetts Department of Conservation & Recreation. Retrieved 2024-03-27.
- ^ a b Porter, Mary; Mikelk, Mary; Bradley, Tom; Therrien, Sue (June 20, 2018). "Berlin Rail Trail Advisory Committee Final Report". Berlin, Massachusetts.
- ^ "Waltham Component of the Wayside Trail, Public Meeting #3, 25% Review" (PDF). Waltham, Massachusetts. 2018-06-04. Retrieved 2024-07-01.
- ^ "MCRT Wayside Branch MEPA Site Walk". Department of Conservation and Recreation. 2013-12-16. Retrieved 2024-10-05.
- ^ "MassDOT Design Guide, Chapter 11, Shared Use Paths and Greenways". Department of Conservation and Recreation. 2017-08-27. Retrieved 2023-09-30.
- ^ a b c d Sullivan Jr., Richard K (2014-01-10). "Certificate of the Secretary of Energy and Environmental Affairs on the Expanded Environmental Notification Form". Massachusetts Executive Office of Energy and Environmental Affairs. Retrieved 2023-09-01.
- ^ Collings, Jesse (2022-03-14). "Waltham set to build new bike path through center of city". Waltham News Tribune. Retrieved 2026-03-11.
- ^ Sandoli, Annie (2022-03-03). "Waltham Mayor Requesting $9.3M For Wayside Rail Trail". Waltham, MA Patch. Retrieved 2024-04-23.
- ^ "Waltham's Wayside Trail Project". Waltham, Massachusetts. Retrieved 2023-08-24.
- ^ "Design of the Waltham Component of the Mass Central Rail Trail – Wayside Branch". Pare Corporation. Retrieved 2024-03-19.
- ^ "DCR Recreational Advisory: Linden Street Bridge". Department of Conservation and Recreation. 2025-12-24. Retrieved 2026-01-12.
- ^ "2022 MassTrails Awards (81 Projects)". MassTrails. 2022-06-30.
- ^ a b c d "2023 MassTrails Grant Awards (68 Projects)". MassTrails. 2023-06-14. Retrieved 2023-09-24.
- ^ a b c d e f g "Mass Central Rail Trail Evaluation of Existing Bridges, Wayside Branch—Waltham to Berlin" (PDF). Massachusetts. 2016-08-01. Archived from the original (PDF) on 2024-11-26. Retrieved 2023-10-05.
- ^ "Past Golden Spike Events". Golden Spike 2023. Retrieved 2023-09-18.
- ^ Brownsberger, Will (2025-12-27). "New Trail Connection". State Senator Will Brownsberger. Retrieved 2025-12-27.
- ^ Kish, Patrice (2024-12-04). "Notice to Proceed RE: MCRT Waltham Linden Street Bridge". Department of Conservation and Recreation. Retrieved 2025-01-22.
- ^ Wangler, Chris (2025-02-27). "Linden Street Bridge Restoration Moving Ahead". WCAC-TV. Retrieved 2025-03-10.
- ^ Van Voorhis, Scott (April 13, 2014). "Progress, at long last, lifts profile of Waltham's 1265 Main". The Boston Globe. Retrieved 2023-08-31.
- ^ a b c MilNeil, Christian (2022-09-19). "Planning Underway for Mass. Central Rail Trail Link Over I-95 in Waltham, Weston". Streetsblog Massachusetts. Retrieved 2023-08-24.
- ^ Stanton, Jr., Vincent (2024-10-28). "Waltham Rail Trail Makes Slow Progress". Belmont Citizens Forum. Retrieved 2024-10-29.
- ^ "Waltham Transportation Presentation—1265 Main Street Development". Weston, Massachusetts. 2024-03-20. Retrieved 2024-03-20.
- ^ a b "Deck level view of Stony Brook Bridge, Weston, Mass., October 21, 2019". Boston and Maine Railroad Historical Society. 2019-10-21. Retrieved 2025-08-26.
- ^ Scott, Peter (1987-12-01). "Application of Linden Street Bridge to National Register of Historic Places" (PDF). p. 2. Retrieved 2025-09-14.
- ^ "Historic Bridge Detail: WSN.904, Central Massachusetts Railroad Bridge (Milepost #12.34)". Massachusetts Historical Commission. 2026-02-28. Retrieved 2026-02-28.
- ^ "Gov. Healey Adds $24 Million for Trail Projects from Pandemic Relief Funds". Streetsblog Massachusetts. 2023-12-21. Retrieved 2023-12-21.
- ^ MilNeil, Christian (2024-04-10). "DCR Starts Construction on Waltham-Weston Mass. Central Trail Connection". Streetsblog Massachusetts. Retrieved 2024-04-11.
- ^ Antonoff, Addison (2025-09-23). "Bike Path Means Smoother Ride for Weston Cyclists". Weston Observer. Retrieved 2025-09-24.
- ^ a b c d e f g h i j Fox, Pamela W. (Spring 2018). "Weston Historical Society Bulletin Vol XLIX, No.1: 1997: Weston Derails the Rail Trail" (PDF). Weston Historical Society. Retrieved 2023-08-24.
- ^ MilNeil, Christian (2019-10-01). "A Network of Rail-Trails Comes Together In Boston's Suburbs". Streetsblog Massachusetts. Retrieved 2024-02-28.
- ^ a b "Mass Central Rail Trail, Weston Rail Trail Underpass". Nitsch Engineering. Retrieved 2024-04-26.
- ^ "The Report | Mass Central Rail Trail". Norwottuck Network. Retrieved 2023-09-16.
- ^ McNamara, Neal (2021-01-06). "Sudbury Mass Central Rail Trail Gets $3M In Transportation Bill". Sudbury, MA Patch. Retrieved 2025-03-10.
- ^ "Project 610660, Sudbury- Wayland- Mass Central Rail Trail (MCRT)". Massachusetts Department of Transportation. 2024-06-23. Retrieved 2024-06-23.
- ^ MilNeil, Christian (2023-03-07). "3 Major MetroWest Trail Projects Are Under Construction In 2023". Streetsblog Massachusetts. Retrieved 2024-12-17.
- ^ a b Rainville, Katelyn M.; Paiva, Marcos (2022-02-14). "Advisory Council on Historic Preservation Electronic Section 106 Documentation Submittal System (e106) Form" (PDF). Sudbury, Massachusetts. Retrieved 2023-09-20.
- ^ "Sudbury-Hudson—Eversource". E.T. & L. Corp. Retrieved 2023-09-20.
- ^ LaHaise, Keven (2024-11-09). "Mass Central Rail Trail Timeline Comes Into Focus". Sudbury Weekly. Retrieved 2024-11-09.
- ^ LaHaise, Kevin (2023-05-12). "Mass Central Rail Trail Planning: Catching Up?". Sudbury Weekly. Archived from the original on 2023-10-12. Retrieved 2023-10-10.
- ^ "Desert Natural Area / Memorial Forest Reservation". Marlborough, Massachusetts. Retrieved 2024-03-19.
- ^ a b "33 Wayside Inn Railroad Waiting Room". Sudbury Historical Society. 2024-10-07. Retrieved 2024-10-08.
- ^ a b LaHaise, ByKevin (2024-10-24). "Sudbury's Second Rail Trail Is Coming Soon". Retrieved 2025-08-25.
- ^ MilNeil, Christian (2025-12-23). "New Trails to Look Forward To In 2026". Streetsblog Massachusetts. Retrieved 2026-01-02.
- ^ "Hudson ARRT Project Status & History". Assabet River Rail Trail. 2010-05-25. Archived from the original on 2023-03-09. Retrieved 2025-02-14.
- ^ a b MilNeil, Christian (2025-10-08). "Healey Administration Announces $7.5 Million in MassTrails Grants". Streetsblog Massachusetts. Retrieved 2025-10-09.
- ^ a b "2025 MassTrails Grant Awards". MassTrails. 2025-09-07. Retrieved 2025-10-11.
- ^ a b Hopkins, Paul (2025-06-26). "Hudson's second rail trail progresses, offers economic development opportunities". Community Advocate. Retrieved 2025-06-27.
- ^ "2024 MassTrails Grant Awards". MassTrails. 2024-06-21. Retrieved 2024-06-21.
- ^ Kussmaul, Caleb (2024-05-05). "Berlin Trail Trust". Berlin Trail Trust. Retrieved 2024-10-07.
- ^ Byrne, Mary (2026-01-28). "Community Path Engineers Submit 100% Design Plan to State". The Belmont Voice. Retrieved 2026-03-12.
- ^ Kussmaul, Caleb (2024-05-05). "Berlin Trail Trust". Berlin Trail Trust. Retrieved 2024-10-07.
- ^ MilNeil, Christian (2025-10-08). "Healey Administration Announces $7.5 Million in MassTrails Grants". Streetsblog Massachusetts. Retrieved 2025-10-09.
- ^ "Hiking areas in Hudson, Massachusetts". Hudson Land Trust. 2020-03-25. Retrieved 2025-05-01.
- ^ "Memorial Forest". Sudbury Valley Trustees. Retrieved 2024-10-16.
- ^ "Conservation Lands & Trails—Maps". Weston, Massachusetts. Retrieved 2023-10-28.
- ^ "The Western Greenway". Waltham Land Trust. Retrieved 2023-09-28.
- ^ a b c Belcher, Jonathan (March 19, 2016). "Changes to Transit Service in the MBTA district 1964–2016" (PDF). NETransit. Retrieved July 25, 2016.
- ^ a b c d The Boston & Maine Railroad Historical Society, Inc. (2008). The Central Mass (Second ed.). Brimfield, MA: Marker Press. ISBN 978-0-9662736-3-2.
- ^ Bedingfield, Robert E. (1977-02-27). "New Chief for a Yankee Railroad". The New York Times. ISSN 0362-4331. Retrieved 2025-06-06.
- ^ Nowell, Rick (2024-01-23). "History of the B&M Railroad". Boston & Maine Railroad Historical Society. Retrieved 2023-08-24.
- ^ Kelly, Jessica G. (2021-04-07). "Town of Sudbury v. Massachusetts Bay Transportation Authority". Boston Bar Association. Retrieved 2026-03-11.
- ^ LaHaise, Kevin (2023-03-03). "MBTA Files Motion To Dismiss Land Court Case 23 MISC 000030". Sudbury Weekly. Archived from the original on 2023-09-30. Retrieved 2023-09-01.
- ^ a b c Gants, Ralph D.; Lenk, Barbara A.; Gaziano, Frank M.; Lowy, David A.; Budd, Kimberly S.; Cypher, Elspeth B.; Kafker, Scott L. (September 22, 2020). "Sudbury vs. Massachusetts Bay Transportation Authority, 485 Mass. 774". Massachusetts Cases. Archived from the original on 2024-02-09. Retrieved 2023-08-25.
- ^ Humphrey, Thomas J. (1996-12-01). "Central Mass. Commuter Rail Feasibility Study" (PDF). Metropolitan Area Planning Council. Retrieved 2023-08-24.
- ^ Tolman, Lynne (1997-04-20). "Wayside rail trail plan in high gear". www.ltolman.org. Telegram & Gazette. Retrieved 2026-02-27.
- ^ Lewis, Cathy Buckley; Kirk, James E. (2017-04-01). "Central Massachusetts Rail Trail Feasibility Study" (PDF). Metropolitan Area Planning Council. Retrieved 2024-10-03.
- ^ "Sudbury, Hudson, Stow, Marlborough". Mass Trail Tracker. 2025-03-18. Retrieved 2025-03-18.
- ^ Williamson, Richard; Mink, Doug (1998-06-02). "Wayside Rail Trail on the Central Mass. Rail Line 1868-1998". MassPaths. Retrieved 2024-10-29.
- ^ Lorant, Richard (1997-12-14). "Town Puts Stick in Spokes of Bikeway Plan". Los Angeles Times. Retrieved 2023-08-25.
- ^ Stanton, Jr., Vincent (2020-03-02). "Community Path Began Decades Ago". Belmont Citizens Forum. Retrieved 2024-09-27.
- ^ Della Penna, Craig (2023-09-24). "A Timeline of the Journey Thus Far to Piece Together The Corridor" (PDF). Mass Central Rail Trail. Retrieved 2023-09-24.
- ^ Massachusetts Bay Transportation Authority and Commonwealth of Massachusetts Department of Conservation and Recreation (December 30, 2010). "Alternative Transportation Corridor Lease Agreement between the MBTA and DCR" (PDF). Sudbury, Massachusetts. Retrieved 2023-08-24.
- ^ a b c Fuchs, Patrick J.; Hedlund, Karen J.; Oberman, Martin J.; Primus, Robert E.; Schultz, Michelle A. (February 2, 2022). "Decision, Docket No. FD 36493, Protect Sudbury Inc. — Petition for Declaratory Order" (PDF). Surface Transportation Board. Retrieved 2023-08-24.
- ^ Cullen, Tom (2017-11-08). "Rail Trail Frequently Asked Questions". Weston, Massachusetts. Retrieved 2024-04-26.
- ^ Della Penna, Craig. "Norwottuck Network Rail Trail Newsletter 11-10 #40". Norwottuck Network. Retrieved 2023-08-24.
- ^ "Mass Central Rail Trail". Weston, Massachusetts. Retrieved 2023-09-24.
- ^ Palmer, Thomas R.; Revers, Lise N.; Bent, Laurie A. (2025-02-25). "Town of Weston Select Board Letter of Support" (PDF). Constant Contact. Retrieved 2025-02-25.
- ^ a b c d e f g Evans, Joan Foster (2019-12-18). "Commonwealth of Massachusetts Energy Facilities Siting Board Final Decision EFSB 17-02 / D.P.U. 17-82 / D.P.U. 17-83". Massachusetts Executive Office of Energy and Environmental Affairs. Retrieved 2023-09-06.
- ^ "Town of Sudbury Town Meetings Proceedings, 2014" (PDF). Sudbury, Massachusetts. 2014-12-09. Retrieved 2025-06-06.
- ^ a b O'Connell, Scott (2015-02-16). "Group looks to revive rail trail". The MetroWest Daily News. Retrieved 2024-10-14.
- ^ Kablack, Jody; Kupfer, Jim (2015-01-07). "Mass Central Rail Trail Letter" (PDF). Sudbury, Massachusetts. Retrieved 2024-10-10.
- ^ "Proceedings, Annual Town Meeting – May 4, 5, 6 & 11, 2015" (PDF). Sudbury, Massachusetts. 2015-05-11. Retrieved 2024-10-14.
- ^ McNamara, Brittney (2016-02-15). "Selectmen, residents want underground wires in Eversource project". Wicked Local. Retrieved 2026-03-11.
- ^ Schultz, Bev (2016-03-24). "Sudbury to Hudson Transmission Reliability Project, Sudbury, Massachusetts, Board of Selectmen Presentation" (PDF). Sudbury, Massachusetts. Retrieved 2023-10-06.
- ^ Chan, Janelle (2017-04-04). "MassDOT Letter" (PDF). Sudbury, Massachusetts. Retrieved 2024-06-21.
- ^ a b Roy, Leo P. (2017-04-18). "The Department of Conservation and Recreation (DCR) letter of support". Massachusetts Executive Office of Energy and Environmental Affairs. Retrieved 2023-09-20.
- ^ Sferra, Kathy (2017-06-06). "Town of Stow Conservation Commission Letter RE: Sudbury-Hudson Transmission Reliability Project/Eversource". Massachusetts Executive Office of Energy and Environmental Affairs. Retrieved 2025-06-13.
- ^ Hinkle, William (2025-01-13). "Eversource Completes Greater Boston and New Hampshire Solution Suite of Transmission Projects with Energization of Sudbury to Hudson Transmission Line". Eversource Energy. Retrieved 2025-01-15.
- ^ a b c Voorhis, Scott Van (2024-04-07). "Don't Let NIMBYs Kill Green Power". Banker & Tradesman. Retrieved 2025-09-04.
- ^ "Attachment A, Sudbury-Hudson Reliability Project, Condition R Compliance Filing". Massachusetts Executive Office of Energy and Environmental Affairs. 2023-06-28. p. 3. Retrieved 2023-09-01.
- ^ Dudek, Martin (2022-02-11). "Historic Properties Avoidance And Protection Plan: Eversource Energy/Massachusetts Department of Conservation and Recreation's Sudbury-Hudson Transmission Reliability and Mass Central Rail Trail Project, Towns of Hudson, Marlborough, Sudbury, and Stow, Middlesex County, Massachusetts, MHC #RC.62384, EEA #15703" (PDF). Sudbury, Massachusetts. Retrieved 2023-09-18.
- ^ Montgomery, Jim (July 7, 2020). "MCRT DCR Response to Delegation" (PDF). Sudbury, Massachusetts. Retrieved November 6, 2023.
- ^ a b c Fuchs, Patrick J.; Hedlund, Karen J.; Oberman, Martin J.; Primus, Robert E.; Schultz, Michelle A. (December 12, 2022). "Decision, Docket No. FD 36623, Rail Line Abutting Landowners—Verified Petition for Declaratory Order" (PDF). Surface Transportation Board. Retrieved 2023-08-24.
- ^ LaHaise, Kevin (2025-03-06). "Eversource Transmission Line Helped Avert FY27 Override". Retrieved 2026-03-09.
- ^ Piper, Gordon H. (2018-09-28). "Sudbury vs. Mass. Bay Transportation Authority, MISC 17-000562". Massachusetts Cases. Archived from the original on 2024-11-28. Retrieved 2023-08-26.
- ^ Lehan, Richard (March 15, 2019). "Recommended Final Decision on Motions to Dismiss for Lack of Standing and Motion to Intervene by Ten Citizen Group, Docket No. 2018-01-RL". Division of Fisheries and Wildlife (Massachusetts). Retrieved 2019-08-26.
- ^ Buckley, Elaine M. (July 27, 2021). "Memorandum of Decision and Order on Cross Motions for Judgement on the Pleadings, Docket No. 2084CV00151" (PDF). Sudbury, Massachusetts. Retrieved 2023-08-24.
- ^ Budd, Kimberly S.; Gaziano, Frank M.; Lowy, David A.; Cypher, Elspeth B.; Kafker, Scott L.; Wendlandt, Dalila Argaez; Georges Jr., Serge (June 25, 2021). "Sudbury vs. Energy Facilities Siting Board, 487 Mass. 737". Massachusetts Cases. Archived from the original on 2025-04-16. Retrieved 2023-08-25.
- ^ LaHaise, Kevin (2023-01-20). "Land Owners to Land Court: Mulligan, Please?". Sudbury Weekly. Archived from the original on 2023-10-03. Retrieved 2023-09-21.
- ^ LaHaise, Kevin (2023-07-14). "Eversource Project: Land Court Case Voluntarily Dismissed". Sudbury Weekly. Archived from the original on 2023-10-04. Retrieved 2023-09-21.
- ^ Freedman, Sarah (2024-05-16). "Town Meeting rejects citizens' petitions regarding MBTA". Community Advocate. Retrieved 2025-11-08.
- ^ "Annual Town Meeting Warrant, Town of Hudson" (PDF). Hudson, Massachusetts. 2024-05-06. Retrieved 2024-10-29.
- ^ Wordell, Joan M.; Malchowski, Jeffrey M. (2024-05-06). "Annual Town Meeting Results" (PDF). Hudson, Massachusetts. Retrieved 2024-10-29.
- ^ Walsh, Evan (2025-03-07) [2025-01-24]. "Hudson Select Board shows interest in Mass. Central Rail Trail". Community Advocate. Retrieved 2025-03-27.
- ^ LaHaise, Kevin (2025-03-27). "Sudbury Select Board Voices Support for Mass Central Rail Trail". Sudbury Weekly. Retrieved 2025-03-27.
- ^ Sullivan, Maureen (2023-04-13). "Assabet River Rail Trail keeps pace with growing communities". Fifty Plus Advocate. Retrieved 2024-08-10.