Jamuna Railway Bridge

Jamuna Railway Bridge

যমুনা রেল সেতু
Jamuna Railway Bridge
Coordinates24°24′09″N 89°46′05″E / 24.4026°N 89.7681°E / 24.4026; 89.7681
CarriesJamtoil–Joydebpur line Dual Gauge railway line
CrossesJamuna River
LocaleSirajganj, & Tangail Bangladesh
Official nameJamuna Railway Bridge
Other nameJamuna Rail Bridge
OwnerBangladesh Railway
Next upstreamNaranarayan Setu
Next downstreamJamuna Bridge
Characteristics
Total length4.8 kilometres (3 mi)
Rail characteristics
Track gaugeDual Gauge
History
Construction startAugust 1, 2020
Construction endNovember 26, 2024
OpenedMarch 18, 2025 (2025-03-18)
Location
Interactive map of Jamuna Railway Bridge

The Jamuna Railway Bridge[1] is a dual-gauge, double-track railway bridge on Jamuna River in Bangladesh. This bridge connects Sirajganj and Tangail by railway network.[2] This bridge is the longest solo railway bridge in Bangladesh.

History and Background

As of October 2020, approximately 44 trains crossed the Jamuna Bridge each day. However, the bridge had several operational limitations. Train speeds were restricted to 20 km/h, and the bridge carried only a single railway track, which limited the number of trains that could cross. In addition, heavy freight trains were unable to use the bridge because of weight restrictions.

The Jamuna Railway Bridge is expected to reduce travel time for trains operating between Dhaka and the northern and western regions of Bangladesh by about two hours. It is also intended to increase capacity for freight transport by rail, including traffic from neighboring countries to the northern regions.

The bridge will facilitate the movement of passengers and goods on domestic routes and is planned to serve as part of regional railway connectivity initiatives such as SAARC, BIMSTEC, SASEC, and the Trans-Asian Railway network. After the new bridge becomes operational, the railway tracks on the Jamuna Bridge are planned to be removed.[3]

Project details

First, on 6 December 2016, the Executive Committee of the National Economic Council (ECNEC) approved the construction project of the bridge.[4] For this, the Bangladesh government undertook the project at a cost of Tk 9,734 crore, of which Japan's development cooperation organization Japan International Cooperation Agency (JICA) will provide Tk 7,724 crore. The project is scheduled to be implemented by December 2023.

However, in the next revised project, the deadline has been extended by two years to December 2025. At the same time, the project cost has been increased from Tk 9,734 crore to Tk 16,781 crore. JICA will provide loan assistance of 72% of the construction cost. Bangladesh Railway will implement the project. This project has been carried out by the Obayashi-Toa-JFE (OTJ) Joint Venture and IHI-SMCC Joint Venture for the eastern and western parts, respectively. Additionally, the project involves constructing a 7.6 km double-line railway approach embankment, 30.73 km of dual-gauge track, 16 viaducts, and renovating the East and West stations and yards of Jamuna Bridge. After completion, the bridge will increase the number of trains that can pass between the capital and the northwest by 88, significantly improving rail connectivity in the region. This bridge can accommodate broad-gauge trains traveling at 120km/h and meter-gauge trains moving at 100km/h.

Jamuna Rail Bridge is the largest and most vivid example of weathering steel (paintless steel) in Bangladesh. Use of this steel eliminates the need of any painting for corrosion protection. The seven year long atmospheric test was conducted by A F M Saiful Amin from Bangladesh University of Engineering and Technology through a joint project with JFe steel corporation Japan as a mark of solidarity and bilateral technology transfer between Japan and Bangladesh.

Progress

The construction of the bridge has been fully completed in November 2024. A test run was initiated on 26 November, that completed the following day. The Jamuna Railway Bridge began trial operations on February 12, 2025, with passenger trains starting to cross the bridge. Initially, trains operated on a single track. The bridge was officially inaugurated on March 18, 2025, marking the start of full operations with both tracks in use. [5][6]

See also

References

  1. ^ "Jamuna rail bridge to be inaugurated late January or early February". Dhaka Tribune. Retrieved 20 December 2024.
  2. ^ Topu, Ahmed Humayun Kabir (18 July 2022). "Bangabandhu Sheikh Mujib Railway Bridge: The next milestone in connectivity". The Daily Star. Archived from the original on 30 April 2024. Retrieved 16 October 2024.
  3. ^ "যমুনায় দ্বিতীয় রেল সেতুর কাজ শুরু নভেম্বরে, ব্যয় বাড়লো দ্বিগুণ" [The second bridge on the Jamuna River]. Bangla Tribune (in Bengali). 19 October 2020. Archived from the original on 25 November 2020. Retrieved 16 October 2024.
  4. ^ প্রতিবেদক, নিজস্ব (7 December 2016). "বঙ্গবন্ধু সেতুর পাশে রেলসেতু হবে" [The bridge will make beside Bangabandhu Bridge]. Prothomalo (in Bengali). Archived from the original on 23 October 2023. Retrieved 16 October 2024.
  5. ^ "Trail train to run across Bangabandhu Railway Bridge Tuesday". Dhaka Tribune. 25 November 2024. Retrieved 29 November 2024.
  6. ^ "Test run over new Jamuna Rail Bridge completed". Bangladesh Sangbad Sangstha. 27 November 2024. Retrieved 29 November 2024.