Ban Phai–Nakhon Phanom Line

Ban Phai–Nakhon Phanom Line
Overview
StatusUnder construction
OwnerState Railway of Thailand
Termini
Stations14
Service
TypeInter-city rail
SystemNorthern Line
Operator(s)State Railway of Thailand
History
Opened2028
Technical
Line length347 km (216 mi)
Number of tracks2
Track gauge1,000 mm (3 ft 3+38 in) metre gauge
Operating speed180 km/h (110 mph)

The Ban Phai–Nakhon Phanom railway line is a new double-track railway project of the State Railway of Thailand and an extension of the Northeastern Railway Line. It will branch off from the Chira–Nong Khai Junction section at Ban Nong Waeng Rai Junction Railway Station in Ban Phai District, Khon Kaen Province, and terminate at the Friendship Bridge 3 Railway Station in Nakhon Phanom Province.

History

The construction project for the double-track railway, Ban Phai, Mukdahan, Nakhon Phanom, according to the original plan, will take 4 years to complete, with a total budget of 66,848.33 million baht.

Sequence of events

Future Schedule
Year Month event
2014 Design project details
2019 May The Cabinet approves the project.
2020 April The National Environment Board has approved the EIA for the project.
2021 March The State Railway of Thailand announced the results of the bidding for two contracts of the project.
September Royal Decree on the expropriation of land for the construction of the Ban Phai-Nakhon Phanom double-track railway line
December 29 Signed a contract for the construction of the Ban Phai-Nakhon Phanom railway line
2022 Expropriate land to support construction (expropriate area approximately 17,499 rai, passing through a total of 6 provinces, 19 districts, 70 sub-districts)

Expropriation value 10,080.33 million baht[1]

2023 March Construction in progress
2024 Construction in progress
2025 August Contract 1 Cumulative plan=72.450% Cumulative performance=42.718% Slower than plan=-29.732%
Contract 2 Cumulative plan=63.646% Cumulative performance=6.901% Slower than plan=-56.745%
Project Overview Cumulative plan=67.952% Cumulative performance=24.418% Slower than plan=-43.534%

List of stations and stops

There are a total of 14 railway stations, 1 railway junction, namely Ban Nong Waeng Rai Railway Junction, where every station is a district or provincial railway station.

Station / Stop Name Distance from the BP. Station level Location note
subdistrict district province
Ban Phai 0 2 Ban Phai Ban Phai Khon Kaen Connect to Northeastern Nong Khai Main Line
Nai Mueang
Ban Nong Waeng Rai Junction 0.300 3 Nai Mueang
Phu Lek 10.072 3 Phu Lek Container yard
Na Pho Halt 20.982 Halt Na Pho Kudrang Maha Sarakham
Kudrang 30.441 3 Kudrang
Borabue 45.812 2 Borabue Borabue
Nong No Halt 59.310 Halt Nong No Maha Sarakham City
Maha Sarakham 69.117 1 Waeng Nang Container yard
Khwao Halt 78.420 Halt Khwao
Si Somdet Halt 85.429 Halt Bodhi Sai Sri Somdet Roi Et
Si Kaew Halt 85.429 Halt Si Kaew Roi Et Province
Roi Et 104.897 1 Yang Yai Janghan Container storage area
Chiang Khwan 117+700 3 Pra Thadu Chiang Khwan
Po Chai 129.093 3 Chiang Mai Pho Chai
Amphoe Phon Thong 150.478 2 Waeng Phon Thong Container yard
Moei Wadi Halt 159.956 Halt Kok Pho Nong Pok
Nong Pok 175.945 3 Nong Pok
Khok Sawang Halt 183.285 Halt Khok Sawang
Hong Chaeng Halt 197.765 Halt Hong Chaeng Leing Nok Tha Yasothon
Loeng Nok Tha 209.666 2 Kudhae
Nikhom Kham Soi 223.100 3 Na Kok Kham Soi Industrial Estate Mukdahan
Ban Bong Daeng Halt 228.100 Halt Nong Waeng
Mukdahan 247.176 1 Mukdahan Mukdahan City
Ban Dan Kham Halt 250.475 Halt
Friendship Bridge 2 254.700 3 Bang Sai Yai Container storage area
Wan Yai 267.899 3 Wan Yai Wan Yai
That Phanom 291.276 2 That Phanom That Phanom Nakhon Phanom
Renu Nakhon 303.948 3 Phon Thong Renu Nakhon
Na Thon Halt 315.426 Halt Na Thon That Phanom
Ban Klang Halt 320.022 Halt Ban Klang
Nakhon Phanom 343.461 1 Na Sai Nakhon Phanom
Friendship Bridge 3 354.783 3 At Samat Container storage area
End of railway track, km 354.783

Construction contract

Contract Period Distance

(kilometers)

Auction winner Progress 6.079%

(Updated as of September 2024)

1 Ban Phai-Nong Phok 180 The A.S.-C.Thawee & Associates Joint Venture consists of A.S. Associate Engineering (1964) Co., Ltd., C.Thawee Construction Co., Ltd., TBTC Joint Venture Co., Ltd., Sermsongwan Construction Co., Ltd., and K.S. Joint Venture Co., Ltd. 12.16%
2 Nong Phok - Friendship Bridge 3 175 The Unique Joint Venture consists of Unique Engineering and Construction Public Company Limited, P.C.E.T. Company Limited, Thai Pikon and Industry Company Limited, and Watcharakhajorn Company Limited. 0.257%

Construction progress

Date[2] Progress Advancement by
January 2025 21.726%
February 2025 23.803% 2.077%
March 2025 26.139% 2.336%
April 2025 31.368% 5.229%
May 2025 34.116% 2.748%
June 2025 37.585% 3.469%
July 2025 40.841% 3.256%
August 2025 42.718% 1.877%
September 2025 44.705% 1.987%
October 2025 45.873% 1.168%
November 2025 47.081% 1.208%

References

  1. ^ "เวนคืนทางคู่ "บ้านไผ่-นครพนม" รถไฟ 6.6 หมื่นล้าน เปิดประเทศเชื่อม AEC" (in Thai). 2021-09-24. Retrieved 2025-12-07.
  2. ^ https://www.srtbanphainongphokc1.com/Result.asp